It starts with a solid foundation: first pile has been driven

Work to further build DECOM Amsterdam is still underway.
After completing installation of Combi Wall (short side) and Sheet piling (long side), pile driving began on Monday, March 15.
The first pile was driven at 8:15 a.m. The entire piling work will take about 10 days.
Subsequently, the concrete quay on the Combi wall side can be installed.
In addition to this work, the dismantling of maritime objects continues. If you have maritime objects such as dry docks and ships that need to be dismantled safely, please contact us.